Top Tips Painting Concrete Floors With Solvent Based Two Pack Epoxy

Painting Bare Concrete Floors with Solvent Based Two Pack Epoxy Floor Coating

 

(Suitable for all traffic)

 

 

  • Two coats of paint are always recommended 1st coat primes and seals the floor. 2nd coat provides good colour build, protection and longevity of the coating.

 

  • Be cautious of using solvent based two pack epoxy over existing floor coatings as solvents may attack the existing paint. If un-sure use solvent free or single pack floor paint.

 

 

  • When painting any concrete floor it is important that the moisture content of the concrete is no greater than 5%.

 

  • Ensure that there is an ambient temperature of 10˚C.

 

  • Green concrete is best left for at least 2-3 months before coating.

 

  • With any floor coating preparation is an essential key to extend the protection and lifespan of the coating.

 

  • To prepare a bare (rough) concrete floor prior to painting we always recommend a light abrasion first; this can be done either by a scarifying machine or track blasting (most effective method). This allows the paint to create a good lock and key effect with the concrete which then leads to much better adhesion.

 

 

  • If the floor has been power floated or is generally very shiny, the floor paint will not adhere to this surface. It is recommended to trackblast the concrete to remove most of the top layer prior to painting.

 

 

  • Two Pack Epoxy as the name suggests has two component that must be mixed together thoroughly to ensure an even cure occurs.

 

  • Two Pack Epoxy’s mixing ratio is 4 parts of paint to 1 part of Two Pack Epoxy Catalyst.

 

  • Two Pack Epoxy as a Pack so there is no confusion to whether the customer needs to purchase the correct catalyst separately. It is important to thoroughly mix the paint 4:1 with the catalyst,

 

  • we recommend mixing with a pneumatic drill and a mixing paddle, to ensure an even dispersion.

 

  • Once the paint has been mixed, let the paint stand for 10-15 minutes before starting to apply.

 

  • Two Pack Epoxy has a mixed pot life of around 8 hours.

 

 

  • Two Pack Epoxy can be easily applied by brush, roller and suitable spray application.

 

  • ENSURE THERE IS GOOD VENTILATION WHEN USING SOLVENT BASED PAINTS.

 

  • Leave the first coat to dry for 12 hours or overnight before overcoating with the second coat.

 

  • If the first coat has been left for 24 hours or more before overcoating then a light abrasion will be required for the second coat to adhere to the first.

 

  • Manufacturer’s guidelines are that any type of paint will need 7 days for the coating to reach its full properties.